based on our actual rate of progress:
"very slow" calcuation:
keys (2 shots/week)
10 shots left = 5 weeks
in-betweens (2 shots/week)
32 shots left = 16 weeks
coloring (2 shots/week)
122 shots left = 61 weeks
backgrounds (2 shots/week)
118 shots left = 59 weeks
= finish the film by end of summer '14
----------------------------------------
"moderate speed" calculation:
keys (4 shots/week)
10 shots left = 3 weeks (01sep13)
in-betweens (4 shots/week)
32 shots left = 8 weeks (15oct13)
coloring (4 shots/week)
122 shots left = 30 weeks (01mar14)
backgrounds (8 shots/week)
118 shots left = 15 weeks (01dec13)
= finish the film by march '14
*if we want to finish the film by december '13, then we need to do a lot better than this, even.
for tomorrow:
• chris, janelle: keys and in-betweens
• eric, ellen: backgrounds
goal is to finish off animation and backgrounds by mid-october so we can all focus on coloring.
for tomorrow:
• chris, janelle: keys and in-betweens
• eric, ellen: backgrounds
goal is to finish off animation and backgrounds by mid-october so we can all focus on coloring.